Contract 74314 REL 43: 1991-029-00 EXP WDFW EMERGING ISSUE/MEASURE SNAKE R FALL CHIN ESU
Project Number:
Title:
Snake River Fall Chinook Research & Monitoring
Stage:
Implementation
Area:
Province Subbasin %
Basinwide - 100.00%
Contract Number:
74314 REL 43
Contract Title:
1991-029-00 EXP WDFW EMERGING ISSUE/MEASURE SNAKE R FALL CHIN ESU
Contract Continuation:
Previous: Next:
n/a
Contract Status:
Closed
Contract Description:
The goal of annual beach seining and PIT tagging activities in Hells Canyon on the Snake River is to tag natural-origin fall Chinook salmon. However, there is always a possibility that a small portion of the sampled population contains subyearling spring/summer Chinook salmon that washout from upstream tributaries that could bias subsequent inferences about the population. Because of this, we collect weekly genetic samples from a subsample of the fish that are collected and tagged to determine whether they are fall-run or spring-run. These percentages can then be used to more accurately predict the abundance of natural-origin fall Chinook salmon that emigrate from Hells Canyon and pass Lower Granite Dam each year. These abundance estimates are used in ongoing life-cycle modeling efforts. Work conducted under this contract will analyze a back-log of samples collected from 2009 to 2018.
Account Type(s):
Expense
Contract Start Date:
09/01/2018
Contract End Date:
08/31/2019
Current Contract Value:
$87,383
Expenditures:
$87,383

* Expenditures data includes accruals and are based on data through 31-Mar-2024.

BPA CO:
Env. Compliance Lead:
Work Order Task(s):
Contract Type:
Release
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract’s location details.

No photos have been uploaded yet for this Contract.

Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Summary of fish origin A: 162. Analyze genetics samples 08/31/2019 08/21/2019
Effective implementation management and timely contract administration B: 119. Manage contract under project 1991-029-00 08/31/2019 08/01/2019

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Chinook (O. tshawytscha) - Snake River Fall ESU (Threatened)
  • 1 instance of WE 162 Analyze/Interpret Data

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 162 Analyze genetics samples 09/01/2018
B 119 Manage contract under project 1991-029-00 09/01/2018
C 132 Annual progress report not required 09/01/2018
D 185 Periodic Status Reports for BPA 09/01/2018